Published: June 2026 Technical Level: Advanced Category: Power Systems Design
Emergency and standby generator systems are required by NFPA 110, NFPA 101, NEC Article 700, and the International Building Code for occupancies where power interruption creates life safety hazards or operational continuity requirements that cannot be met by the utility supply alone. NFPA 110-2022 classifies these systems by the maximum allowable transfer time and minimum operational duration, and establishes maintenance, testing, and installation requirements that govern the service life and reliability of the installed equipment. This paper develops the generator sizing methodology from first principles, covering load classification, harmonic de-rating for variable frequency drive loads, motor starting voltage dip analysis, fuel system design for required operational duration, and the ATS transfer scheme selection that determines the system's response to utility disturbances. The design procedure is applied to a 150 kW, 480 V, three-phase emergency system for a healthcare facility with NEC Article 517 compliance requirements, yielding a final generator rating of 225 kW and a fuel storage volume of 660 gallons for 96 hours of operation.
Emergency power systems are one of the most consequential elements of a building's electrical infrastructure: they are rarely called upon, but when they are, the stakes are often human life. A generator that fails to start, produces insufficient voltage, or shuts down prematurely during a hospital power failure can directly affect patient outcomes in operating rooms, intensive care units, and life support areas. For this reason, NFPA 110 establishes prescriptive requirements not only for system design but for ongoing maintenance and testing — obligations that are often underweighted in facilities management programs and that represent a significant fraction of long-term system lifecycle cost.
NFPA 110-2022 defines five classification dimensions for emergency and standby power systems. The Type designation (Type 10, Type 60, Type 120) specifies the maximum time from loss of normal power to restoration of power to the load, in seconds. Level 1 systems serve loads whose failure represents a direct threat to human life; Level 2 systems serve loads whose failure would not directly threaten life but would cause significant operational disruption. Class designations (Class 2, Class 6, Class 48, Class 72, Class Ext) specify the minimum fuel supply for continuous operation in hours. For healthcare facilities under NFPA 99-2021, the requirements are more specific: essential electrical systems must be Type 10 (10-second transfer) or Type 0 (immediate, for critical care areas), Level 1, and Class 96 or longer depending on local AHJ requirements.
NFPA 70 Article 700 requires that loads connected to the emergency system be classified as life safety loads, critical operations loads, or optional standby loads. The distinction matters for generator sizing because different load categories have different transfer switch requirements and different design standards. Life safety loads must be served by the emergency system within the time limit specified by the system Type classification and cannot be shed to reduce generator loading. Critical operations loads may be served by the emergency system with a lower priority than life safety loads. Optional standby loads are the lowest priority and may be on automatic load-shedding contactors that drop these loads if the generator approaches its rated capacity.
For the healthcare case study, the load inventory produces the following category breakdown: life safety loads (lighting in means of egress, fire alarm, exit signs, essential ventilation) total 18 kW; critical care loads (operating room equipment, ICU support, nurse call, emergency receptacles in patient care areas) total 84 kW; and equipment system loads (refrigeration for medications, select HVAC, elevators serving upper floors) total 48 kW. The sum is 150 kW of active power demand.
Not all loads in each category operate simultaneously at their nameplate rating. NFPA 110 and NEC Article 220 permit demand factors to be applied to the aggregate load if engineering judgment or load measurement supports a value below unity. For the healthcare case study, the operating room equipment load carries a demand factor of 0.85 (not all ORs occupied simultaneously), reducing the OR contribution from 55 kW to 46.75 kW. The HVAC load carries a demand factor of 0.70 for the emergency mode (fans at reduced speed, not serving non-essential zones), reducing it from 30 kW to 21 kW. The adjusted aggregate continuous load is 138 kW.
Generators are rated in kVA at a specified power factor, typically 0.8 lagging per NEMA MG1-22.43. The kW rating at the nameplate power factor is 80 percent of the kVA rating. For a load mix with a system power factor of 0.82 lagging (typical for a mix of motor, lighting, and UPS loads), the required kVA is:
Where: is the required generator apparent power capacity.
is the total active power demand of all served loads in kW.
is the weighted average power factor of all served loads.
The next standard generator frame size above 168 kVA at 0.8 PF nameplate is typically 200 kVA (160 kW). This is the minimum continuous rating before applying the derating factors developed in Sections 3 and 4.
Variable frequency drives, uninterruptible power supplies, and LED drivers draw non-sinusoidal current waveforms that contain harmonic components in addition to the fundamental 60 Hz current. Harmonic currents flow through the generator's armature winding and produce losses proportional to the square of the harmonic current amplitude multiplied by the per-unit harmonic frequency (due to the frequency-dependent skin effect in the armature conductors). The total harmonic derating factor for the generator is:
Where: is the harmonic derating factor (0 to 1, where 1 means no derating).
is the per-unit harmonic current of order , normalized to the fundamental current.
is the harmonic order.
For the healthcare case study, the UPS systems and VFDs produce a combined harmonic spectrum with a total harmonic distortion of 28 percent, dominated by the 5th (20%) and 7th (15%) harmonics. The derating factor calculates to approximately 0.91, requiring the generator to be oversized by a factor of 1/0.91 = 1.10 to maintain the same available continuous kW output.
Generator output capacity decreases with increasing altitude (reduced air density reduces cooling effectiveness and combustion efficiency) and with increasing ambient temperature above the design basis of 40°C. NFPA 110 Section 7.2 requires that the generator nameplate rating be derated to the actual site conditions before verifying compliance with the load requirement. For an installation at 1,500 m above sea level, the altitude derating factor is approximately 0.93 (7% reduction per 1,000 m above sea level per NEMA MG1 guidelines). Combined with the harmonic derating of 0.91, the effective derated output of a 200 kVA generator is:
This is below the required 138 kW, so the 200 kVA frame is insufficient. The next standard size, 250 kVA (200 kW nameplate), yields a derated output of kW, which exceeds the 138 kW requirement with a margin of 22 percent. The 250 kVA generator is therefore the minimum compliant rating before accounting for motor starting transients.
Motor starting imposes a transient kVA demand on the generator that can be three to seven times the motor's rated kVA, lasting for two to five seconds until the motor accelerates to running speed. During this period, the generator voltage dips because the AVR cannot instantly compensate for the sudden reactive demand. If the voltage dip exceeds 15 percent of nominal (the NFPA 110 limit for Level 1 systems), equipment connected to the emergency bus may trip on undervoltage, defeating the purpose of the emergency system.
The voltage dip under locked rotor conditions is approximated by:
Where: is the fractional voltage dip (0 to 1).
is the motor locked rotor (starting) kVA, typically 5 to 7 times the motor running kVA.
is the generator rated kVA (subtransient, from the generator's reactance data).
For the largest motor in the healthcare system — a 20 hp chilled water pump at 480 V three-phase — the locked rotor current is approximately 6 times the full-load current of 24 A, giving a locked rotor kVA of kVA. With a 250 kVA generator, the voltage dip is percent — well above the 15 percent limit.
To reduce the voltage dip to an acceptable level, the design options are: increase the generator kVA rating to reduce the ratio; apply a soft starter or VFD to the pump motor to reduce the starting kVA; or use a generator with a lower subtransient reactance . For this case study, specifying a generator with pu (low-reactance design) and adding a soft starter to the chilled water pump reduces the starting kVA to 60 kVA, yielding a voltage dip of percent — still marginal. Increasing the generator to 300 kVA (240 kW) achieves percent, within the 15 percent limit after accounting for AVR boost response. The final selected rating is 300 kVA (225 kW derated), which also provides adequate margin for load growth.
The transient voltage depression during motor starting is illustrated in Figure 1, which plots the generator terminal voltage through a large motor start and recovery.

Figure 1. Generator terminal voltage during a large motor start. The horizontal axis is time in seconds and the vertical axis is voltage in per unit. The voltage dips sharply when the motor inrush current is drawn against the generator's subtransient reactance, then recovers as the machine accelerates and the voltage regulator responds. The engineer should observe that the minimum voltage must remain above the tolerance of the connected equipment — typically not below about 0.80 p.u. — which frequently sets the generator rating above what the steady-state load alone would require.
The fuel consumption rate for a diesel generator at rated load is:
Where: is the fuel consumption at 100 percent rated load in gallons per hour.
is the thermal efficiency factor, approximately 14.7 kWh per gallon of diesel at rated load.
At 75 percent load (the anticipated average loading for the healthcare system):
For Class 96 operation (96 hours continuous per NFPA 110 Class Ext requirements for many healthcare AHJs), the minimum fuel storage volume is:
Where: is the required fuel storage volume in gallons.
is the required operational duration in hours.
is a safety factor of 1.10, accounting for fuel delivery uncertainty and tank design volume above the minimum usable volume.
The tank must be located to satisfy both NFPA 30 (flammable liquids storage) and local fire code requirements, with a sub-base tank or above-ground tank with secondary containment per EPA 40 CFR 112. For installations in seismic zones, the tank and fuel supply piping must be designed per ASCE 7 and NFPA 110 Section 7.9.
NFPA 110 Section 6.4 requires automatic transfer switches that initiate on loss of normal power and transfer the load to the emergency generator within the system Type time requirement. The transfer switch must be rated for the continuous current of the emergency load and must be listed for emergency service (UL 1008). Open-transition transfer — where the load is momentarily disconnected before being reconnected to the generator — is standard for most NFPA 110 applications and produces a transfer-interruption of 100 ms to 300 ms (acceptable for Type 10 systems). Closed-transition transfer — where the generator is synchronized with the utility before transfer, producing a break of less than 100 ms — is required for sensitive electronic loads that cannot tolerate even brief interruption and is standard for operating room ATS in NFPA 99 critical care applications.
The ATS must be tested monthly under load per NFPA 110 Section 8.4, with the generator loaded to at least 30 percent of rated capacity during the test to prevent wet stacking in diesel engines. Full-load tests are required annually. These testing obligations must be incorporated into the facility's maintenance program as a standing contractual requirement, not left to ad hoc scheduling.
The analysis in this paper connects to several companion studies in this library. Readers concerned with the upstream and downstream engineering will find Battery Energy Storage for Backup Power develops a closely related aspect of the same problem, while Healthcare Essential Electrical Systems extends the treatment into an adjacent domain. For the broader methodological context, Data Center Power System Design provides complementary depth.
Emergency and standby generator sizing under NFPA 110 and NEC Article 700 is a multi-constraint problem in which the base load rating is only the starting point, and the methodology developed in this paper shows that harmonic derating for nonlinear loads, altitude and temperature derating, and the motor-starting voltage-dip limit each can govern the final kVA selection. The central engineering conclusion is that the binding constraint is frequently the transient voltage dip during the largest motor start rather than the steady-state load, because the generator's subtransient reactance and its limited overload capability produce a voltage depression that must remain within the tolerance of the connected equipment. The fuel-system sizing then ties the rating to the mandated operational duration, since NFPA 110 specifies minimum run times that determine storage volume. For the practicing engineer, the operative discipline is to size against all the controlling constraints simultaneously — base load with demand factors, harmonic and environmental derating, starting voltage dip, and fuel autonomy — and to select the rating set by the most restrictive of them, because an emergency system that cannot start its largest motor or sustain its required duration fails its life-safety purpose.
[1] NFPA 110, Standard for Emergency and Standby Power Systems, 2022 edition, NFPA, 2022.
[2] NFPA 99, Health Care Facilities Code, 2021 edition, NFPA, 2021.
[3] NFPA 70, National Electrical Code, Articles 700, 701, 702, 517, 2023 edition, NFPA, 2023.
[4] NEMA MG1-2021, Motors and Generators, NEMA, 2021.
[5] IEEE Standard 446-1995, Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications (Orange Book), IEEE, 1995.
[6] IEEE Standard 141-1993, Recommended Practice for Electric Power Distribution for Industrial Plants (Red Book), IEEE, 1993.
[7] Caterpillar Inc., Generator Set Sizing Guide, Application and Installation Guide LEBE0007, Caterpillar, 2024.
[8] Cummins Power, Generator Application Manual, Technical Manual T-030, Cummins, 2024.
[9] J. C. Das, Power System Analysis: Short-Circuit Load Flow and Harmonics, 2nd ed., CRC Press, 2011.
[10] NFPA 30, Flammable and Combustible Liquids Code, 2021 edition, NFPA, 2021.